Sunnyvale, CA
Home MenuConstruction Waste
Notice: Penalty for Not Meeting Diversion Rates
Effective Jan. 1, 2022 per Ordinance 3183-21 (Amendment) and Municipal Code 16.74.070
If your project fails to meet the 65% diversion rate requirement, you must pay a penalty. The penalty applies to projects with permits issued this year. It also applies to projects started in prior years and submitted for final inspection in 2022.
- Penalty formula: Square footage x (65% - [actual diversion rate]) = $Total penalty
- Example: 2,045 sq ft x (.65 - .61) = $818
For more information email Alyssa Hagerbrant.