In May 2003, the Sunnyvale City Council approved a phased project approach for construction of a downtown plaza at 200 West Evelyn Ave. The urban park was designed and constructed on top of the underground parking structure of the Mozart Development (Mathilda Place). Construction of Phase I was completed in 2004. It opened to the public as Plaza del Sol.
A City project to design and construct Plaza del Sol Phase II was originally scheduled for 2012-2014. However, the funding was rescheduled multiple times. Funding changes were due to developments in the downtown area, budget needs or competing priorities. Phase II includes design features left out of the initial project due to insufficient funding. It adds features based on experience with the initial project. The intent is to create a landmark focal point on Plaza del Sol to encourage Sunnyvale residents and guests to visit.
Timeline
- September 2021 - Award design contract
- April 2021 - Advertise RFP
- September 2020 - Begin RFP process for a landscape architect
- August 11, 2020 - Present final concept to City Council
- July 8, 2020 - Present preferred concept to the Parks and Recreation Commission